No. of Printed Pages: 4 IBCE-0621
DIPLOMA IN CIVIL ENGINEERING DCLE(G) 009S2 Term-End Examination December, 2016
BCE-062 CONSTRUCTION SUPERVISION AND BUILDING MAINTENANCE
Time hours Maximum Marks: 70
Note: Question no. 1 is compulsory. Attempt any (our out of the remaining questions.
Write True or False for the following statements:
Bricks need to be cured for 24 hours before use.
D.P.C. is sometimes made of cement concrete also.
Workers below the age of 18 should not be allowed at project site.
If cement is kept for six months, its strength reduces by 30%.
20.4 bags of cement are required per cubic metre of mix for 1 ratio.
In Flemish Bond in every course, one brick is kept in Header position and next in Stretcher position.
Construction Joints and Expansion Joints are same in concrete slab.
(viii) Rolling shutters are normally made from wide strips of steel having thickness of 1.25 mm.
Define the following: 3x2=6
Crown in Road (show in sketch)
Sub-Grade
Lap Joint in Timber (sketch)
2. Explain/define the following terms in a building: 4x2=8
Balcony
Basement
Carpet Area
FAR (Floor Area Ratio)
How does a supervisor monitor the progress of the work Explain any method of monitoring.
3. Explain in detail, the methodology for the execution of the following at a project site
Site clearance
Laying and marking of plan at site for foundation
Shoring and Timbering in earthwork
Termite treatment before construction
4. What are the roles and responsibilities of a Security Supervisor at site How does it affect the work at site?
List out the means and provisions for security to be arranged at a project site including traffic, material and personnel. 7+7=14
5. Explain with sketches the following types of flooring:
Bricks or Interlocking Flooring
Terrazzo Flooring
Glazed Tile Flooring
Wooden Flooring
6. Give a neat sketch of a manhole duly labelled and explain the construction methodology in steps.
How many types of drain pipes are available in the market (from material point of view)? Explain the use of PVC and cast iron pipes with reasons. 7+7=14
7. Write short notes on the following:
Difference between internal and external painting
Methodology of fixing a door in a room/cubical
Role of construction supervisor
Documents and registers to be maintained in a store
DIPLOMA IN CIVIL ENGINEERING DCLE(G) 009S2 Term-End Examination December, 2016
BCE-062 CONSTRUCTION SUPERVISION AND BUILDING MAINTENANCE
Time hours Maximum Marks: 70
Note: Question no. 1 is compulsory. Attempt any (our out of the remaining questions.
Write True or False for the following statements:
Bricks need to be cured for 24 hours before use.
D.P.C. is sometimes made of cement concrete also.
Workers below the age of 18 should not be allowed at project site.
If cement is kept for six months, its strength reduces by 30%.
20.4 bags of cement are required per cubic metre of mix for 1 ratio.
In Flemish Bond in every course, one brick is kept in Header position and next in Stretcher position.
Construction Joints and Expansion Joints are same in concrete slab.
(viii) Rolling shutters are normally made from wide strips of steel having thickness of 1.25 mm.
Define the following: 3x2=6
Crown in Road (show in sketch)
Sub-Grade
Lap Joint in Timber (sketch)
2. Explain/define the following terms in a building: 4x2=8
Balcony
Basement
Carpet Area
FAR (Floor Area Ratio)
How does a supervisor monitor the progress of the work Explain any method of monitoring.
3. Explain in detail, the methodology for the execution of the following at a project site
Site clearance
Laying and marking of plan at site for foundation
Shoring and Timbering in earthwork
Termite treatment before construction
4. What are the roles and responsibilities of a Security Supervisor at site How does it affect the work at site?
List out the means and provisions for security to be arranged at a project site including traffic, material and personnel. 7+7=14
5. Explain with sketches the following types of flooring:
Bricks or Interlocking Flooring
Terrazzo Flooring
Glazed Tile Flooring
Wooden Flooring
6. Give a neat sketch of a manhole duly labelled and explain the construction methodology in steps.
How many types of drain pipes are available in the market (from material point of view)? Explain the use of PVC and cast iron pipes with reasons. 7+7=14
7. Write short notes on the following:
Difference between internal and external painting
Methodology of fixing a door in a room/cubical
Role of construction supervisor
Documents and registers to be maintained in a store
Other Question Papers
Departments
- Centre for Corporate Education, Training & Consultancy (CCETC)
- Centre for Corporate Education, Training & Consultancy (CCETC)
- National Centre for Disability Studies (NCDS)
- School of Agriculture (SOA)
- School of Computer and Information Sciences (SOCIS)
- School of Continuing Education (SOCE)
- School of Education (SOE)
- School of Engineering & Technology (SOET)
- School of Extension and Development Studies (SOEDS)
- School of Foreign Languages (SOFL)
- School of Gender Development Studies(SOGDS)
- School of Health Science (SOHS)
- School of Humanities (SOH)
- School of Interdisciplinary and Trans-Disciplinary Studies (SOITDS)
- School of Journalism and New Media Studies (SOJNMS)
- School of Law (SOL)
- School of Management Studies (SOMS)
- School of Performing Arts and Visual Arts (SOPVA)
- School of Performing Arts and Visual Arts(SOPVA)
- School of Sciences (SOS)
- School of Social Sciences (SOSS)
- School of Social Work (SOSW)
- School of Tourism & Hospitality Service Sectoral SOMS (SOTHSM)
- School of Tourism &Hospitality Service Sectoral SOMS (SOTHSSM)
- School of Translation Studies and Training (SOTST)
- School of Vocational Education and Training (SOVET)
- Staff Training & Research in Distance Education (STRIDE)
Subjects
- Construction Equipment
- Construction Management
- Construction Supervision and Building Maintenance
- Irrigation Engineering
- Prestressed Concrete
- Soil Mechanics and Foundation Engineering
- Technical Documentation
- Transportation Engineering