Exam Details
Subject | flexible manufacturing system | |
Paper | ||
Exam / Course | m.tech | |
Department | ||
Organization | Institute Of Aeronautical Engineering | |
Position | ||
Exam Date | July, 2017 | |
City, State | telangana, hyderabad |
Question Paper
Hall Ticket No Question Paper Code: BCC006
INSTITUTE OF AERONAUTICAL ENGINEERING
(Autonomous)
M.Tech II Semester End Examinations (Regular) July, 2017
Regulation: IARE-R16
FLEXIBLE MANUFACTURING SYSTEMS
(CAD/CAM)
Time: 3 Hours Max Marks: 70
Answer ONE Question from each Unit
All Questions Carry Equal Marks
All parts of the question must be answered in one place only
UNIT I
1. Explain various modes of manufacturing in flexible manufacturing systems.
What are the different problems concerned in regular manufacturing process.
2. Explain what is low volume manufacturing of small batch manufacturing and their applications.
What are the aims, technical performance, improve order development and objects of flexible
manufacturing systems.
UNIT II
3. Explain backward scheduling approach in manufacturing, period of time and delivery with finite
capacity loading.
Distinguish between Real time vs.- discrete event control.
4. What is a dead lock in modeling. what are strategies used for dealing with dead locks.
Explain forward scheduling approaches with infinite capacity loading.
UNIT III
5. A 20 station transfer line is being proposed to machine a certain component currently produced
by conventional methods. The proposal received from the ma. chine tool builder states that the
line will operate at a production rate of 50 pc/hr at 100% efficiency. From similar transfer lines,
it is estimated that breakdowns of all types will occur with a frequency F 0.10 breakdown per
cycle and that the average downtime per line stop will be 8.0 min. The starting casting that is
machined on the line costs 3.00 per part. The line operates at a cost of 75.00/hr. The 20
cutting tools (one tool per station) last for 50 parts each, and the average cost per tool 2.00
per cutting edge Based on this data, compute the following:
i. Production rate
ii. Line efficiency
iii. Cost per unit piece produced on the line
Write a short note on limitations of simulation and factors of level of realism.
Page 1 of 2
6. Write a brief note on Petrinets and places of transition of Perinet.
Explain in brief the concept Markov Chains and process with examples if necessary.
UNIT IV
7. Explain about tools, equipment, resource capabilities and optimizing manufacturing systems?
Explain the manufacturing system analysis in flexible manufacturing systems.
8. Explain the heuristic oriented approach in flexible manufacturing systems.
Explain the transient analysis of manufacturing facilities in demand.
UNIT V
9. Write a note on acceptance sampling to develop inspection plan.
Explain the difficulties in implementation of flexible manufacturing systems.
10. Explain the dual card system of KANBAN with diagram.
Explain the methods of Deburring in flexible manufacturing systems.
INSTITUTE OF AERONAUTICAL ENGINEERING
(Autonomous)
M.Tech II Semester End Examinations (Regular) July, 2017
Regulation: IARE-R16
FLEXIBLE MANUFACTURING SYSTEMS
(CAD/CAM)
Time: 3 Hours Max Marks: 70
Answer ONE Question from each Unit
All Questions Carry Equal Marks
All parts of the question must be answered in one place only
UNIT I
1. Explain various modes of manufacturing in flexible manufacturing systems.
What are the different problems concerned in regular manufacturing process.
2. Explain what is low volume manufacturing of small batch manufacturing and their applications.
What are the aims, technical performance, improve order development and objects of flexible
manufacturing systems.
UNIT II
3. Explain backward scheduling approach in manufacturing, period of time and delivery with finite
capacity loading.
Distinguish between Real time vs.- discrete event control.
4. What is a dead lock in modeling. what are strategies used for dealing with dead locks.
Explain forward scheduling approaches with infinite capacity loading.
UNIT III
5. A 20 station transfer line is being proposed to machine a certain component currently produced
by conventional methods. The proposal received from the ma. chine tool builder states that the
line will operate at a production rate of 50 pc/hr at 100% efficiency. From similar transfer lines,
it is estimated that breakdowns of all types will occur with a frequency F 0.10 breakdown per
cycle and that the average downtime per line stop will be 8.0 min. The starting casting that is
machined on the line costs 3.00 per part. The line operates at a cost of 75.00/hr. The 20
cutting tools (one tool per station) last for 50 parts each, and the average cost per tool 2.00
per cutting edge Based on this data, compute the following:
i. Production rate
ii. Line efficiency
iii. Cost per unit piece produced on the line
Write a short note on limitations of simulation and factors of level of realism.
Page 1 of 2
6. Write a brief note on Petrinets and places of transition of Perinet.
Explain in brief the concept Markov Chains and process with examples if necessary.
UNIT IV
7. Explain about tools, equipment, resource capabilities and optimizing manufacturing systems?
Explain the manufacturing system analysis in flexible manufacturing systems.
8. Explain the heuristic oriented approach in flexible manufacturing systems.
Explain the transient analysis of manufacturing facilities in demand.
UNIT V
9. Write a note on acceptance sampling to develop inspection plan.
Explain the difficulties in implementation of flexible manufacturing systems.
10. Explain the dual card system of KANBAN with diagram.
Explain the methods of Deburring in flexible manufacturing systems.
Other Question Papers
Subjects
- ac to dc converters
- advanced cad
- advanced concrete technology
- advanced data structures
- advanced database management system
- advanced mechanics of solids
- advanced reinforced concrete design
- advanced solid mechanics
- advanced steel design
- advanced structural analysis
- advanced web technologies
- big data analytics
- computer aided manufacturing
- computer aided process planning
- computer architecture
- computer oriented numerical methods
- cyber security
- data science
- data structures and problem solving
- dc to ac converters
- design for manufacturing and assembly
- design for manufacturing mems and micro systems
- design of hydraulic and pneumatic system
- distributed operated system
- earthquake resistant design of buildings
- embedded c
- embedded networking
- embedded real time operating systems
- embedded system architecture
- embedded system design
- embedded wireless sensor networks
- english for research paper writing
- finite element method
- flexible ac transmission systems
- flexible manufacturing system
- foundations of data science
- foundations of data sciences
- fpga architecture and applications
- hardware and software co-design
- high performance architecture
- intelligent controllers
- internet of things
- introduction to aerospace engineering
- mathematical foundation of computer
- mathematical methods in engineering
- matrix methods of structural analysis
- micro controllers and programmable digital signal processing
- multilevel inverters
- numerical method for partial differential equations
- power electronic control of ac drives
- power electronic control of dc drives
- power quality
- precision engineering
- principles of distributed embedded systems
- programmable logic controllers and their applications
- rapid prototype technologies
- rehabilitation and retrofitting of structures
- renewable energy systems
- research methodology
- soft computing
- special machines and their controllers
- stress analysis and vibration
- structural dynamics
- structural health monitoring
- theory of elasticity and plasticity
- theory of thin plates and shells
- web intelligent and algorithm
- wireless lan’s and pan’s
- wireless lans and pans
- wireless sensor networks