Exam Details
Subject | Elements of Survey | |
Paper | ||
Exam / Course | Diploma in Civil Engineering (DCLE) | |
Department | School of Engineering & Technology (SOET) | |
Organization | indira gandhi national open university | |
Position | ||
Exam Date | December, 2015 | |
City, State | new delhi, |
Question Paper
1. Select the most appropriate answer for each of the following questions
The following sights are taken on a turning point:
Fore sight only
Back sight only
Fore sight and Back sight
Fore sight and Intermediate sight
Geodetic survey is different from plane survey because of
undulations of the topography
coverage of very large area
the curvature of the Earth
the large difference of elevation between various points
The length of chain is measured from
centre of one handle to centre of other handle
outside of one handle to outside of other handle
outside of one handle to inside of other handle
inside of one handle to inside of other handle.
A fixed point of reference elevation is known as
Reduced level
Benchmark
Change Point
Instrument Station
If the plotted position of an instrument station is not known, the most accurate orientation of the plane table can be achieved by
Trough compass
Back sighting
Observation of two well-defined points
Observation of three well-defined points
The operation consisting of revolving the telescope through 1800 in a vertical plane about its horizontal axis is called
Transiting
Face left
Face right
Traversing
The whole circle bearing of a line is 60°. Its quadrantal bearing is
N 60° E
E 60° N
S 60° W
W 60° S
2. Briefly discuss the following:
Purpose of surveying.
Classification of survey based on the instruments used.
What is an offset Describe the offset method.
A survey map is required to be drawn to a scale of 1110,000 RF. A 20 m chain was used which was· found to be accurate at the commencement of work while 10 cm too long at the closure. The area of the plot surveyed was found to be 90 cm^2 on the map. Calculate the actual area of the plot.
Define the following:
Angle of dip
Magnetic Declination
Local Attraction
Magnetic Bearing
Explain the temporary adjustments of theodolite.
5. Describe Lehmann's Rule with the help of a neat sketch.
6. The following staff readings were observed with a level:
2.225, 1·605, 0.985, 2.090, 2·865, 1.260, 0·605, 1·985, 1.045, 2·685
the instrument having been moved after third, sixth and eighth readings. Enter the above readings in a page of a level book and· calculate the R.L. of the above points, if the first reading was taken with a staff held on a Bench Mark of R.L. 412·385 m.
What is the difference between a prismatic compass and a surveyor's compass?
Explain with a neat sketch the construction and working of a cross staff.
The following sights are taken on a turning point:
Fore sight only
Back sight only
Fore sight and Back sight
Fore sight and Intermediate sight
Geodetic survey is different from plane survey because of
undulations of the topography
coverage of very large area
the curvature of the Earth
the large difference of elevation between various points
The length of chain is measured from
centre of one handle to centre of other handle
outside of one handle to outside of other handle
outside of one handle to inside of other handle
inside of one handle to inside of other handle.
A fixed point of reference elevation is known as
Reduced level
Benchmark
Change Point
Instrument Station
If the plotted position of an instrument station is not known, the most accurate orientation of the plane table can be achieved by
Trough compass
Back sighting
Observation of two well-defined points
Observation of three well-defined points
The operation consisting of revolving the telescope through 1800 in a vertical plane about its horizontal axis is called
Transiting
Face left
Face right
Traversing
The whole circle bearing of a line is 60°. Its quadrantal bearing is
N 60° E
E 60° N
S 60° W
W 60° S
2. Briefly discuss the following:
Purpose of surveying.
Classification of survey based on the instruments used.
What is an offset Describe the offset method.
A survey map is required to be drawn to a scale of 1110,000 RF. A 20 m chain was used which was· found to be accurate at the commencement of work while 10 cm too long at the closure. The area of the plot surveyed was found to be 90 cm^2 on the map. Calculate the actual area of the plot.
Define the following:
Angle of dip
Magnetic Declination
Local Attraction
Magnetic Bearing
Explain the temporary adjustments of theodolite.
5. Describe Lehmann's Rule with the help of a neat sketch.
6. The following staff readings were observed with a level:
2.225, 1·605, 0.985, 2.090, 2·865, 1.260, 0·605, 1·985, 1.045, 2·685
the instrument having been moved after third, sixth and eighth readings. Enter the above readings in a page of a level book and· calculate the R.L. of the above points, if the first reading was taken with a staff held on a Bench Mark of R.L. 412·385 m.
What is the difference between a prismatic compass and a surveyor's compass?
Explain with a neat sketch the construction and working of a cross staff.
Other Question Papers
Departments
- Centre for Corporate Education, Training & Consultancy (CCETC)
- Centre for Corporate Education, Training & Consultancy (CCETC)
- National Centre for Disability Studies (NCDS)
- School of Agriculture (SOA)
- School of Computer and Information Sciences (SOCIS)
- School of Continuing Education (SOCE)
- School of Education (SOE)
- School of Engineering & Technology (SOET)
- School of Extension and Development Studies (SOEDS)
- School of Foreign Languages (SOFL)
- School of Gender Development Studies(SOGDS)
- School of Health Science (SOHS)
- School of Humanities (SOH)
- School of Interdisciplinary and Trans-Disciplinary Studies (SOITDS)
- School of Journalism and New Media Studies (SOJNMS)
- School of Law (SOL)
- School of Management Studies (SOMS)
- School of Performing Arts and Visual Arts (SOPVA)
- School of Performing Arts and Visual Arts(SOPVA)
- School of Sciences (SOS)
- School of Social Sciences (SOSS)
- School of Social Work (SOSW)
- School of Tourism & Hospitality Service Sectoral SOMS (SOTHSM)
- School of Tourism &Hospitality Service Sectoral SOMS (SOTHSSM)
- School of Translation Studies and Training (SOTST)
- School of Vocational Education and Training (SOVET)
- Staff Training & Research in Distance Education (STRIDE)
Subjects
- Advanced Survey
- Applied Mechanics
- Chemistry
- Computer Basics
- Concrete Technology
- Construction Drawing
- Construction Technology- I
- Construction Technology- II
- E/M Engineering
- Electrical Technology
- Electronics
- Elementary Civil Engineering
- Elements of Survey
- Engineering Drawing
- Engineering Materials
- Environmental Engineering
- Estimating & Quantity Surveying- I
- Estimating & Quantity Surveying- II
- Fluid Mechanics
- Heat Power Technology
- Industrial Management
- Machine Drawing
- Mathematics-I
- Mathematics-II
- Physics
- Refrigeration & Air-Conditioning
- Strength of Materials
- Theory of Structures- I
- Theory of Structures- II
- Workshop Technology